Zhoukou-Huaiyang gas pipeline non-stop plugging reconstruction project

Due to the river reconstruction of Xingfu River and Liusha River in Zhoukou, the river will be dug down to an elevation of about 42.12 meters after the reconstruction, and the part of the line located in the river will be exposed at the bottom of the river.

2024

07-12

"Help Salt Mountain to Develop and Build a Beautiful Hometown"-Jinshiwan People Fulfill Their Responsibilities with Practical Actions!

This project is located in Yanshan County, Cangzhou City. It is a thousand-year-old county with a long history. It is known as the hometown of thousands of children and the first hometown of overseas Chinese in Chinese history. It is known as "Phoenix City.

2024

06-12

Zhoukou-Huaiyang gas pipeline non-stop plugging reconstruction project

Due to the river reconstruction of Xingfu River and Liusha River in Zhoukou, the river will be dug down to an elevation of about 42.12 meters after the reconstruction, and the part of the line located in the river will be exposed at the bottom of the river.

2024

06-12

Jingmen South Bridge Valve Room Reconstruction Ball Taking Project Construction Perfect End!

On or about June 10, the owner of Jingmen found that the detection ball was stuck during the inspection in the pipeline, which required the company to seal the problem with pressure.

2024

06-12

Do not forget your initiative mind Strives for Progress

At 14:00 on March 29, Laiwu Xinao Gas Subhigh Pressure Pipeline Mouth Town Wanglou Village Sewage Treatment Plant occupied pressure, blocked and diverted the project. With the efforts of 10 warriors in Jinshiwan, they completed this task safely and efficiently, and were highly appraised and recognized by Party A. "Defend the pipeline safely, let the customer rest assured", our footsteps never stop!

2024

06-12

Dingbian Oil Transmission Three φ 377 Four-seal Line Change Project Completed Perfectly!

The Jinghui oil pipeline was completed and put into operation in September 2003, starting from the first station in Jing'an and finally at the end of Hui'an Fort. The total length of the pipeline is 216.65km, the operating pressure is 0.7 -3.5MPa, the ф diameter is 377mm, and the pipeline material is X52 as the main conveying medium for purified oil.