Jingmen South Bridge Valve Room Reconstruction Ball Taking Project Construction Perfect End!

Release time:

2024-06-12


On or about June 10, the owner of Jingmen found that the detection ball was stuck during the inspection in the pipeline, which required the company to seal the problem with pressure.

After receiving the task, the company quickly organized personnel to assemble the equipment and machines, and the equipment and machines were ready to be loaded at 18:00 p.m. on June 15. Arrived at the destination on the evening of June 16. On June 17, he entered the site, assisted in the excavation of Jianghan oil construction operation pit, equipment transportation, and on-site equipment and tools sorting, and conducted safety education and training, deepening safety awareness!

The roads on the construction site are all country roads, which are very narrow. All kinds of small intersections do not know the way for navigation. I got lost once. As it was raining that day, the road was too slippery, too narrow, and the car was too large to get in. I had to use the truck to hoist the equipment. These are not the only difficulties. By June 18, there was little heavy rain and light rain, and it was difficult to get into the crane. Two excavators assisted the crane, and the two operation pits were completed only with excavators and cranes. Jinshiwan people have always believed that "the solution is always more difficult than the difficulty".

When entering the construction site on the 6.18 day, the staff removed anti-corrosion from the pipeline and measured the wall thickness of the pipeline. Pipe fitting assembly and welding, opening, iron cutting and plugging test tightness; For example, in the welding process, the operating pressure of the pipeline is 0Mpa and cannot be welded for a long time. Welders need to observe the pipeline temperature at any time for the safety of the pipeline during the welding process. Due to the high temperature of the pipeline, safety, safety, there will be safety problems; it was not until 3: 00 a.m. the next day that the task of the day was completed, and every link was very rigorous, and there was no slack because of the tight schedule of the task.

On June 19, the construction site gathered at 6: 00 a.m. was pumped out, cut off the pipe, hit the butter wall, and connected.

On June 20, the workload was unsealed and the blind plate was installed, and the flaw detection film was qualified.

On June 21, the workload equipment was transported and loaded with the truck crane to prevent corrosion and the construction was completed.

This construction has received unanimous praise from the owners and supervisors, and verbal praise, saying that we forget to sleep and eat, and that our work is orderly, and that our work is very efficient, which reflects the spirit of young people. I believe Jinshi Bay will get better and better!