Zhoukou-Huaiyang gas pipeline non-stop plugging reconstruction project
Project name: Zhoukou-Huaiyang gas pipeline non-stop plugging reconstruction project
Project overview:
Due to the river reconstruction of Xingfu River and Liusha River in Zhoukou, the river will be dug down to an elevation of about 42.12 meters after the reconstruction, and the part of the line located in the river will be exposed at the bottom of the river.
In view of this situation, Zhoukou city natural gas co., ltd. decided to rerouted the gas pipelines in this part of the river to meet the requirements of river reconstruction. the new and old pipelines are required to adopt the technology of eight seals and eight blocks without pressure. The total length of the diversion of the two rivers is about 384 meters.
Plan of Liusha River before Reconstruction
Plan of Liusha River after Reconstruction
On April 20, 2020, the company's project manager drove 600 kilometers to the construction site in Zhoukou City, Henan Province, and formulated the construction plan. The project will be officially started on May 6. As the terrain of the area through which the project passes is mainly rivers with large topographic relief, the pipeline construction along the line will be carried out by means of mechanized flow operation of assembly and welding under the ditch.
Construction site
Piping
Pipe pair welding
Rust removal and anti-corrosion of weld
After 20 days of fighting, the two rivers, 384 meters of pipeline welding, anti-corrosion joint coating, pipeline trench, pipeline pressure test, pigging and drying, and trench backfilling, etc. All for the final link, and the most important one, that is, blocking the hot work.
Due to the particularity of the operation, and can ensure the normal gas supply of 5 million people's families in eight counties and three districts around Zhoukou City, Zhoukou Natural Gas Company attached great importance to it and invited Zhoukou TV station to interview on the spot.
Cao Dayong, the project manager, put forward: "Everyone talks about safety, everything is safe, always want to be safe, and everywhere should be safe." Fine operation of each link ensures the quality of the project, covers all dust, and uses the concept of environmental protection to build a green and civilized construction site.
Blocking Captain Yao Yuanjun Accepts Interview
standardized construction
Zhou Huai's line change project department gave full play to the spirit of defying hardships and dangers and making progress head-on. Through team discussion, adjustment of personnel structure and refinement of business process, the main project was completed on June 4, 17 days ahead of schedule. It has been unanimously recognized and praised by the owner and the supervisor.