Do not forget your initiative mind Strives for Progress-A

Release time:

2024-05-27


In March, spring returns to the earth and everything recovers. This is a season full of vitality, and it is also a beautiful, magical and hopeful season.

However, when the "epidemic" was still not over, the warriors of Jinshi Bay drove 300 kilometers to embark on the journey, using their actions to demonstrate the noble quality of the Uyghur people who gave up their small homes for everyone.

On March 20, we received a notice that a Φ 273-time high-pressure natural gas pipeline needed to be relocated to a safe range due to the government's planned construction of a sewage treatment plant, which was under pressure with the planned construction. As the equipment of downstream enterprises needed normal ventilation, Jinshiwan was entrusted to use non-stop transmission and plugging technology to relocate the pipeline.

 

图片1_副本

 

Project manager Liu Hui and team leader Li Chao immediately worked out the construction plan. After comprehensive consideration, it is planned to use the four-seal non-stop plugging process to complete the line change and change project, and carry out personnel training, safety disclosure and technical disclosure. Captain Li Chao stressed the size of the construction process matters. Everything is put into practice, safe and prepared.

 

1b3a7868196276800672bf5ae5932bb 500b71bbf72444d7e772738b100d5fa

 

On March 22, the warriors of Jinshiwan arrived at the construction site. Under the premise of safety and efficiency, every operation was carried out in a standard and orderly manner.

 

73945442f52a3ce495bb5bb5e666975 f368a20712eabb900262798f85c88b3

Installation of welding tee fittings Installation of tapping machine and drilling

 

1788670226aaedc325bb9804e233495 38a2e0198d1a9171798e658d58c0a7e

 

Prefabrication of bypass pipeline

 

b8773b7324a1e3eddea346ee9783490

 

Plugging

 

56f2ec8a115139423d6c6fb6f17460a 0e33f4760ad18d051ec7b6ed14f4a00

 

New and old pipeline connections (downstream) New and old pipeline connections (upstream)

 

5c39f0a4a98829fc84705e0261ca429 3dd45eac63c671bf5286509d779265e

 

Plug the rear lid safety blind and complete the corrosion protection work.

"If you don't accumulate silicon, you can't reach thousands of miles. If you don't accumulate small streams, you can't become a river or a sea". Every rescuer must be a risky "retrograde", not afraid of difficulties in order to safeguard the safety of people's lives and property, brave and willing to contribute! ".

At 14:00 on March 29, Laiwu Xinao Gas Subhigh Pressure Pipeline Mouth Town Wanglou Village Sewage Treatment Plant occupied pressure, blocked and diverted the project. With the efforts of 10 warriors in Jinshiwan, they completed this task safely and efficiently, and were highly appraised and recognized by Party A. "Defend the pipeline safely, let the customer rest assured", our footsteps never stop!